When layout isn’t an issue, but your kitchen is still outdated, doing a kitchen replacement is a great option. PEGASUS recently completed this kitchen replacement in Arlington. Check out the cost breakdown for this newly up-to-date kitchen!
Sample Kitchen Replacement Cost Breakdown | |
Job Phase | Gross Total Costs |
Permits | $1,218 |
Project Management | $2,173 |
Site Preparation | $724 |
Demolition | $1,789 |
Dumpster | $746 |
Framing | $1,037 |
Exterior Trim | $312 |
Siding | $994 |
Millwork & Trim | $1,743 |
Cabinets | $9,145 |
Counters | $3,195 |
Insulation | $852 |
Exterior Doors | $2,130 |
Drywall | $1,491 |
Hardwood | $1,970 |
Tile | $1,349 |
Painting | $1,917 |
Specialties | $682 |
Plumbing | $4,883 |
HVAC | $277 |
Electrical | $10,650 |
Grand Total | $49,276 |