When layout isn’t an issue, but your kitchen is still outdated, doing a kitchen replacement is a great option. The budget below includes full demolition / replacement of kitchen, new cabinets, counters, floors plumbing and electrical.
Job Phase | Costs |
Permits | 1,615 |
Project Management | 2,386 |
Site Preparation | 3,550 |
Material Run | 167 |
Demolition | 2,863 |
Dumpster | 2,059 |
Framing | 4,075 |
Millwork & Trim | 1,560 |
Cabinets | 13,746 |
Counters | 4,225 |
Insulation | 1,079 |
Drywall | 2,982 |
Hardwood | 2,343 |
Tile | 1,846 |
Painting | 1,278 |
Specialties | 795 |
Plumbing | 6,674 |
HVAC | 277 |
Electrical | 12,070 |
Grand Total | 65,589 |