When layout isn’t an issue, but your kitchen is still outdated, doing a kitchen replacement is a great option. The budget below includes full demolition / replacement of kitchen, new cabinets, counters, floors plumbing and electrical.
| Job Phase | Costs |
| Permits | 1,615 |
| Project Management | 2,386 |
| Site Preparation | 3,550 |
| Material Run | 167 |
| Demolition | 2,863 |
| Dumpster | 2,059 |
| Framing | 4,075 |
| Millwork & Trim | 1,560 |
| Cabinets | 13,746 |
| Counters | 4,225 |
| Insulation | 1,079 |
| Drywall | 2,982 |
| Hardwood | 2,343 |
| Tile | 1,846 |
| Painting | 1,278 |
| Specialties | 795 |
| Plumbing | 6,674 |
| HVAC | 277 |
| Electrical | 12,070 |
| Grand Total | 65,589 |