Wakefield, MA · Lakeside

Wakefield Attic Conversion with Primary Suite

13 weeks
of construction
~480 sq ft
renovated
1 new stair
up to the third floor
3 spaces
primary bedroom, bath, family room

The project

The owners lived on the second floor of a two-family house, with an attic above that held little more than storage boxes, an old chimney and bare roof boards. As parents, they wanted a space of their own. They asked us for a real staircase up, a primary bedroom with its own bathroom, a storage room, a dormer, the chimney gone, and new heating and cooling.

The old house kept us guessing. It turned out to be balloon framed, with wall studs running unbroken from floor to roof, which took some clever beam work below the windows to carry the new loads. Our structural engineer reviewed it, and we went with deeper 2x12 rafters so the new roof could hold more insulation, plus a flush steel beam and LVLs to carry the new stair opening. Getting water and drains to a third-floor bath meant running a new stack and risers up from the basement through the closets below.

On the second floor we took out the old chimney and walls to open the family room for a new staircase with oak treads and black iron balusters, turned a radiator wall into a stone-faced gas fireplace, and did some minor work in the kitchen. The old boiler and radiators came out for a new system. Upstairs, the new bath has Carrara marble hex floors, white subway tile, a glass walk-in shower with a bench, a double vanity and matte black fixtures.

What's included

AtticDormerPrimary suiteBathroomFamily room

Add-ons

Stone-faced gas fireplaceNew oak staircase to the third floorSteel beam and old chimney removedNew heating and cooling system (boiler and radiators out)New windows and roofBalloon-frame beam work below the windows

Before and after

Before: Family room: the radiator wall became a stone gas fireplace with a granite hearth and mantel, plus a new closet beside it.BEFORE
After: Family room: the radiator wall became a stone gas fireplace with a granite hearth and mantel, plus a new closet beside it.AFTER
Family room: the radiator wall became a stone gas fireplace with a granite hearth and mantel, plus a new closet beside it.
Before: Family room: walls and the old chimney came out to open the room and make space for a new oak stair to the third floor.BEFORE
After: Family room: walls and the old chimney came out to open the room and make space for a new oak stair to the third floor.AFTER
Family room: walls and the old chimney came out to open the room and make space for a new oak stair to the third floor.
Before: Outside: a new dormer on the side roof gave the attic the headroom for a primary suite.BEFORE
After: Outside: a new dormer on the side roof gave the attic the headroom for a primary suite.AFTER
Outside: a new dormer on the side roof gave the attic the headroom for a primary suite.

The floor plan, before and after

Existing floor plan
Existing third floor (attic)
New floor plan
New third floor with the primary bedroom, bath and storage
Attic primary bathroom in Wakefield, MA with a frameless glass shower, white subway tile, built-in bench and separate toilet roomFront of the house in Wakefield, MA after the attic conversion, with the new dormer on the third floor

Finishes we used

Cabinets
Schrock Pleasant Hill maple, square doors in Moonstone for the primary bath vanity.
Tile
Carrara polished 2-inch hex on the bath floor, shower floor and niche; Seda white gloss 4x12 shower walls.
Fixtures
Matte black throughout: Delta Trinsic faucets and shower trim, Kohler rainhead and handshower; white undercounter sinks; Kohler skirted toilet.
Counters
Vanity top and shower details cut from stone remnants.

Questions about this project

What did this Wakefield attic conversion include?

A primary bedroom, a bathroom with a glass walk-in shower and double vanity, a storage room and a dormer on the third floor, plus a new oak staircase up from the second-floor family room and a stone-faced gas fireplace.

What made this attic hard to convert?

The house is balloon framed, with wall studs running unbroken from floor to roof, so it took careful beam work below the windows to carry the new loads. We also used deeper 2x12 rafters for more insulation and a flush steel beam and LVLs for the new stair opening.

How did plumbing get to a third-floor bathroom?

We ran a new stack and water risers up from the basement through closets on the floors below.

How long did construction take?

About 13 weeks from the start of construction to completion.