Kitchen remodeling in Melrose, Arlington and nearby towns

A full kitchen remodel with PEGASUS costs about $70,000–$125,000 when the layout stays and $130,000–$225,000 when it opens to the rooms around it. Construction takes 3–5 months, after 4–6 weeks of design. Ranges are the middle half of what homeowners paid on our 2020–2025 projects, change orders included, appliances not.

194
kitchens built
117
of them included a bath, addition or more
4.9★
on Houzz, 40 reviews
25 yrs
in Melrose · MA HIC 137663
What it costs

Most kitchens aren't just kitchens

117 of our 194 kitchen jobs took in something else: a bath, a mudroom, an addition. Here is how the price grows as the project does. Same numbers as our cost guide, because they come from the same table.

Kitchen, layout stays5 projects · 3–5 months
about $70k–$125k
Kitchen opened to adjoining rooms16 projects · 3–5 months
$130k–$225k
Kitchen and bathroom14 projects · 15–22 weeksKitchen and bath remodeling →
$165k–$360k
Addition with kitchen and bath24 projects · 18–29 weeksKitchen additions →
$355k–$545k

Bars on one scale, $0–$550k. Includes labor, materials, permits, project management and change orders. Appliances are separate; you buy them and we install them. Design is its own agreement: 1.5% of the construction estimate, with a $1,000 retainer to start. Design usually takes 4–6 weeks.

Where the money goes

A $150,000 kitchen, by trade

Cabinets and counters
23% · $34,500
Carpentry, windows, doors
20% · $30,000
Electrical
16% · $24,000
Walls, floors, tile, paint
14% · $21,000
Plumbing and heating
11% · $16,500
Demo, dumpster, site prep
9% · $13,500
Permits and project mgmt
7% · $10,500

Across 21 projects like this we built from 2020 to 2025. Why electrical is so high: older homes often need new circuits for today's appliances, and sometimes a panel or service upgrade. Cabinets are the biggest single choice you'll make, and the easiest place to move your price up or down.

How long it takes

A sample kitchen schedule

Before we start: 4–6 weeks of design, 1–2 months for permits, and every selection made at least 45 days ahead so the schedule holds. Then about 12 weeks on site when nothing has to wait, and 3–5 months on most real jobs.

Demolition
Framing
Windows and exterior trim
Rough plumbing, heat, electrical
Rough inspection ◆ payment
Insulation and plaster
Hardwood ◆ payment
Interior trim
Cabinets
Counter fabrication
Paint ◆ payment
Finish electrical
Hardwood finish
Counters, backsplash, plumbing
Punch list, final ◆ payment
Wk 1Wk 3Wk 5Wk 7Wk 9Wk 11

Black = rough work, gold = finishes, light gold = counters being made after templating. ◆ = a payment, so you pay as the work reaches each stage. Daily logs and a Friday summary in Buildertrend the whole way. Based on our standard kitchen schedule; other work in your project is added to it, and your schedule is set before you sign.

Our work

Three kitchens, start to finish

See all our projects →

Where we've built them

Kitchens we've built, by town

Kitchens we've built, by town. Towns with their own page link there; the rest open our projects filtered to kitchens in that town.

In our clients' words
“We had our kitchen redone, and they had great ideas on layout and materials. They were extremely organized and communicative… And we love our new kitchen.”
Paula K. · Winchester kitchen
“I was tremendously grateful for the daily communication from the project manager… my kitchen was completed exactly on timeline.”
Helen · Kitchen renovation

Read all our reviews on Google →

Common questions
How much does a kitchen remodel cost in Greater Boston?

On our 2020–2025 projects, about $70,000–$125,000 when the layout stays and $130,000–$225,000 when the kitchen opens to the rooms around it. Adding a bathroom puts most projects at $165,000–$360,000.

How long does a kitchen remodel take?

3–5 months of construction, after 4–6 weeks of design and 1–2 months for permits.

Are appliances included?

No. You buy the appliances and decorative lighting; we install them. We order and deliver everything else.

Will the price change during construction?

Your agreement is a fixed price with allowances for the finishes you pick. It changes only if you change the job or choose finishes above an allowance.

Do you offer a warranty?

Yes, one year on our work.

By Geoff Shafer, owner. Has run PEGASUS in Melrose for 25 years; MA licensed Construction Supervisor and registered HIC (HIC 137663). Updated .
Thinking about your kitchen?
In a 15-minute call I can tell you where your kitchen is likely to land in its range and what would move it up or down. No cost, no pressure. — Geoff