Arlington Second-Story Addition
The project
This was a one-story ranch. Every bedroom and the only full bath sat on the main floor, right off the kitchen and living room.
We measured the house and spent the winter and spring on design. We drew several ways to add space, from shed dormers to hip, cross-gable and craftsman-style roofs, and rendered three versions of the front before settling on a full second story with board-and-batten gables and standing-seam metal roofs over the entry and a wide bank of front windows. Upstairs there are four bedrooms, including a primary suite with a vaulted ceiling, two baths and a walk-in closet. Downstairs, two of the old bedrooms became a new entry with an open stair, a mudroom and a pantry.
Building a new floor on top of an older house takes careful framing. The original walls were 2x4, so we set new 2x10 floor framing, built the new walls in 2x6 and added LVL headers over the existing first-floor windows. We pinned down details early, like the trim brackets under the roof overhangs and the sloped bedroom ceiling, so there were fewer surprises on site. The new space beat the Massachusetts energy code by almost 12%.
What's included
Add-ons
Before and after
BEFORE
AFTER
BEFORE
AFTER
BEFORE
AFTERThe floor plan, before and after




Finishes we used
Questions about this project
Can you add a second story to a ranch in Arlington?
Yes. Here we added a full second floor with four bedrooms, a primary suite with a vaulted ceiling, two baths and a walk-in closet, and turned two old first-floor bedrooms into a new entry, open stair, mudroom and pantry.
What does it take structurally to build on top of an older house?
The original walls were 2x4, so we set new 2x10 floor framing, built the new walls in 2x6 and added LVL headers over the existing first-floor windows.
How long did construction take?
About 31 weeks from the start of construction to completion.
What do projects like this cost?
Additions with a bathroom that we built from 2020 to 2025 typically ran $205k to $360k. Your price is set in a fixed-price agreement before work starts.