Kitchen and bath remodeling in Melrose, Arlington and nearby towns

On our 2020–2025 projects, a kitchen remodel together with a bathroom cost $165,000–$360,000 and took 15–22 weeks to build, after 4–6 weeks of design and 1–2 months for permits. Ranges are the middle half of what homeowners paid, change orders included, appliances not.

117
of our kitchens since 2003 took in a bath, addition or more
460
projects since 2003
4.9★
on Houzz, 40 reviews
25 yrs
in Melrose · MA HIC 137663
What it costs

How the price builds

Doing the kitchen and a bath together is one project, one schedule and one crew. Here is how the ranges compare. Same numbers as our cost guide, because they come from the same table.

Bathroom on its own8 projects · 10–15 weeksBathroom remodels →
$50k–$70k
Kitchen opened to adjoining rooms16 projects · 3–5 monthsKitchen remodeling →
$130k–$225k
Kitchen and bathroom together14 projects · 15–22 weeks
$165k–$360k
Kitchen and bath in a new addition24 projects · 18–29 weeksKitchen additions →
$355k–$545k

Bars on one scale, $0–$550k. Includes labor, materials, permits, project management and change orders. Appliances are separate; you buy them and we install them.

Where the money goes

A $250,000 kitchen and bath, by trade

Cabinets and counters
18% · $45,000
Carpentry, windows, doors
22% · $55,000
Electrical
14% · $35,000
Walls, floors, tile, paint
18% · $45,000
Plumbing and heating
12% · $30,000
Demo, dumpster, site prep
10% · $25,000
Permits and project mgmt
6% · $15,000

Across 14 projects like this we built from 2020 to 2025. Cabinets, tile and plumbing fixtures are the choices that move these projects most.

How long it takes

A sample kitchen and bath schedule

Before we start: 4–6 weeks of design, 1–2 months for permits, and every selection made at least 45 days ahead so the schedule holds. Then about 13 weeks on site when nothing has to wait, and 15–22 weeks on most real jobs.

Demolition
Framing
Windows and exterior trim
Rough plumbing, heat, electrical
Rough inspection ◆ payment
Insulation and plaster
Hardwood ◆ payment
Bath tile
Interior trim
Cabinets
Counter fabrication
Paint ◆ payment
Finish electrical
Hardwood finish
Counters, backsplash, plumbing, shower door
Punch list, final ◆ payment
Wk 1Wk 3Wk 5Wk 7Wk 9Wk 11Wk 13

Black = rough work, gold = finishes, light gold = counters being made after templating. ◆ = a payment, so you pay as the work reaches each stage. Daily logs and a Friday summary in Buildertrend the whole way. Based on our standard kitchen and bath schedule; other work is added to it, and your schedule is set before you sign.

Our work

Three kitchen and bath projects, start to finish

See all our projects →

In our clients' words
“We recently had Pegasus renovate our kitchen and both bathrooms. We’re talking removing a wall, moving radiators, upgrading electrical, moving plumbing and appliances—the kind of job we knew would overwhelm us really quickly. Thankfully we chose Pegasus, who made the whole thing pretty easy.”
Catherine · Melrose kitchen and two baths · Houzz
“The demo was complete in record time and dust in my temporary kitchen was minimal. The bathrooms are beautiful, thanks guys. I would use this group again and recommend them highly.”
Joanne · Kitchen and baths · Angi

Read all our reviews on Google →

Common questions
How much does a kitchen and bath remodel cost in Greater Boston?

On our 2020–2025 projects, a kitchen and bathroom done together ran $165,000–$360,000. A kitchen opened to the rooms around it ran $130,000–$225,000 on its own, and a simple bathroom $50,000–$70,000.

How long does a kitchen and bath remodel take?

15–22 weeks of construction, after 4–6 weeks of design and 1–2 months for permits.

Why do the kitchen and bath together?

One design, one permit, one schedule and one crew. The trades are already on site, and the house is torn up once instead of twice.

Are appliances included?

No. You buy the appliances and decorative lighting; we install them. We order and deliver everything else.

Will the price change during construction?

Your agreement is a fixed price with allowances for the finishes you pick. It changes only if you change the job or choose finishes above an allowance.

By Geoff Shafer, owner. Has run PEGASUS in Melrose for 25 years; MA licensed Construction Supervisor and registered HIC (HIC 137663). Updated .
Planning a kitchen and a bath?
In a 15-minute call I can tell you where your project is likely to land in its range and what would move it up or down. No cost, no pressure. — Geoff