Our second-story additions built from 2020 to 2025 cost about $215,000–$394,000 (the middle half of 8 jobs, change orders included) and took about 18 weeks of construction, after design, engineering and permits. A second story adds bedrooms and baths without giving up the yard.

27
second-story additions since 2003
145
additions of all kinds
4.9★
on Houzz, 40 reviews
25 yrs
in Melrose · MA HIC 137663
What it costs

What additions cost

Most second stories add bedrooms and at least one bathroom. These are the closest ranges in our cost guide, from the same table.

Addition with a bathroom18 projects · 16–20 weeksHome additions →
$205k–$360k
Addition with a kitchen and bathroom24 projects · 18–29 weeksKitchen additions →
$355k–$545k
Whole-house renovation13 projects · about 4–5 monthsWhole-house remodels →
$335k–$550k

Bars on one scale, $0–$550k. Includes labor, materials, permits, project management and change orders.

Where the money goes

A $275,000 addition with a bathroom, by trade

Cabinets and counters
3% · $8,250
Carpentry, windows, doors
42% · $115,500
Electrical
12% · $33,000
Walls, floors, tile, paint
18% · $49,500
Plumbing and heating
10% · $27,500
Demo, dumpster, site prep
8% · $22,000
Permits and project mgmt
7% · $19,250

Across 18 projects like this we built from 2020 to 2025. Most of an addition is the shell: foundation, framing, roof, siding and windows. That is why carpentry leads.

How long it takes

A sample second-story schedule, about 18 weeks on site

Before we start: 4–6 weeks of design, stamped structural plans and the building permit, and every finish picked at least 45 days ahead. The sample below is about 18 weeks.

Structural prep and roof removal ◆ payment
Second-floor framing and new roof (dry-in) ◆ payment
Windows and siding
Interior demo and framing
Rough plumbing, heat, electrical
Rough inspection ◆ payment
Insulation and plaster
Bath tile, flooring starts ◆ payment
Hardwood
Interior trim
Vanities and built-ins
Paint ◆ payment
Finish electrical and plumbing
Hardwood finish
Punch list and final ◆ payment
Wk 1Wk 3Wk 5Wk 7Wk 9Wk 11Wk 13Wk 15Wk 17

Black = outside and rough work, gold = finishes. ◆ = a payment. Daily logs and a Friday summary in Buildertrend the whole way. Based on our standard addition schedule; your schedule is set before you sign.

Our work

Three second-story projects, start to finish

See all our projects →

In our clients' words
“The project was completed on budget and quicker than the initial time projection.”
Lara R. · Arlington addition · Google
“A year later, we love the new addition and feel grateful to have chosen Pegasus for our project.”
Aaron P. · Addition · Houzz

Read all our reviews on Google →

Common questions
How much does a second-story addition cost in Greater Boston?

Our second stories built from 2020 to 2025 ran about $215,000–$394,000 (the middle half of 8 jobs, change orders included). Size, bathrooms and how much of the first floor changes move the price most.

How long does a second-story addition take?

About 18 weeks of construction on a typical job, after design, engineering and permits.

Can my house hold a second story?

A licensed structural engineer checks the existing framing and foundation and stamps the plans before we apply for the permit. Some houses need new beams, posts or footings, and that is priced in your estimate.

Will zoning allow it?

Height and setback limits differ by town. We look up your lot and zoning before design starts.

Will the price change during construction?

You sign a fixed price with allowances for the finishes you pick. It changes only if you change the job or choose finishes above an allowance.